When the Site Is Not Ready: The Employer’s Obligation to Provide Access and Possession in Construction Projects 20 November 2026

Who is responsible when a construction site is not ready? We explore an employer’s obligation to prepare and provide access to a site under an international standard form, the relevant principles under Thai law and decisions by Thai courts and public authorities.

The employer’s obligation to provide site access and possession

Under Section 587 of the Thai Civil and Commercial Code, a construction contract is generally treated as a contract for hire of work. The contractor agrees to complete specified work for the employer and the employer agrees to pay remuneration for the completed work.

That definition might suggest that the employer’s principal obligation is to pay the contract price. In practice, however, construction projects are complex and depend on coordination among many participants, including the employer, design and project engineers, consultants, quantity surveyors, main contractors, subcontractors and relevant public authorities.

The employer’s obligations therefore extend beyond making payments. Where the contract requires the contractor to perform work at a particular site and within a specified period, the employer may also need to ensure that the site is ready and that the contractor can access and use it. Setting a commencement date without making the site available can lead to disputes over who caused the delay, whether liquidated damages may be imposed on the contractor and whether the employer must bear costs arising from an extension of time.

"Setting a commencement date without making the site available can lead to disputes over who caused the delay, whether liquidated damages may be imposed on the contractor and whether the employer must bear costs arising from an extension of time."

Site access and readiness under an international standard form

The FIDIC Red Book 2017 (Reprinted 2022 with Amendments), published by the International Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conseils), is widely used for employer-designed construction projects.

Sub-Clause 2.1 expressly requires the employer to give the contractor access to and possession of the site. The timing must be specified in the Contract Data. If no time is specified, access and possession must be provided when needed to allow the contractor to proceed in accordance with the programme or, if no programme is available, the initial programme submitted under Sub-Clause 8.3.

The obligation may extend beyond access to the land itself. Where the contract requires the employer to give the contractor possession of a foundation, structure, plant or means of access, the employer must do so at the time and in the manner stated in the specification. The employer may, however, withhold the relevant right or possession until it has received the performance security.

If the employer fails to provide the required access or possession on time, and the failure is not caused by the contractor, the contractor may claim a time extension and/or payment of the resulting cost plus profit under Sub-Clause 20.2. The contractor will not be entitled to that relief to the extent that the employer’s failure was caused by an error or delay on the contractor’s part, including an error or delay in submitting a relevant contractor’s document.

The clause therefore treats access and possession as practical requirements for carrying out the work and not merely as a formal right to enter the site.

The employer’s obligation under Thai law

Thai law recognises the principle of pacta sunt servanda meaning that contractual obligations should be performed as agreed. If a construction contract clearly requires the employer to provide access to the site or make it ready for construction, that obligation will generally be assessed under the terms of the contract.

In practice, however, Thai construction contracts, especially contracts with public-sector employers, may state the contractor’s obligation to commence work by a specified date without expressly setting out the employer’s corresponding obligation to provide a ready site. This can raise questions about the scope of the employer’s obligations and the consequences of failing to meet them.

Where a contract is silent, Thai decisions have tended to focus on whether circumstances prevented the contractor from performing its work. In other words, the key issue is often whether the site or a necessary approval was unavailable in a way that materially affected the contractor’s ability to proceed.

Supreme Administrative Court Judgment Red Case No. Aor.97/2568

In Supreme Administrative Court Judgment Red Case No. A.97/2568, the contractor could not complete a project to improve an existing municipal waste-disposal area and convert it into a controlled disposal site at a landfill in Prachuap Khiri Khan .

Before handing over the site, the employer had not obtained the legally required land-use permission. It still could not provide the site by the contractual completion deadline. The court considered that performance had become impossible because of circumstances arising after the obligation was created and attributable to the employer, not the contractor. The contractor was therefore released from its obligation to perform and was entitled to the counter-performance and damages arising from the employer’s non-performance.

"The contractor could not begin the work without the site being provided."

Office of the Attorney General Determination No. Hor.50/2538

The Office of the Attorney General has also considered whether the contractor could proceed with the work. In Determination No. Hor.50/2538, a public-sector employer knew that approval from the Uthai Thani Highway District was required before pipes could be laid and driven beneath a highway. The employer did not obtain approval in advance and the contractor was ordered to stop work and wait for it for 33 days.

The Office considered the delay to have resulted from the employer’s administrative failure. Although the contractor completed the work 26 days after the contractual deadline, the delay was attributable to circumstances for which the contractor was not responsible. The employer therefore could not impose a penalty for late completion.

Supreme Court Judgment No. 6407/2545

Supreme Court Judgment No. 6407/2545 illustrates that an obligation to provide the site may be implied even if the contract does not expressly say so.

The contract required the contractor to widen a road and install drainage pipes, kerbs and footpaths, and specified the place and date the work was to begin. The court considered that the employer was required to prepare the site for construction and make it available from the stated commencement date. Although the contract did not expressly address site handover, the site was understood to be under the employer’s responsibility, control or use. The contractor could not begin the work without the site being provided.

The site contained obstacles, including electricity poles and cables, water pipes and parts of third-party buildings. The court considered that it was for the employer to address those obstacles. Requiring the contractor to proceed only in unobstructed areas could have conflicted with the contractual work sequence. Work affecting another person’s land or property could also expose the contractor to criminal proceedings for trespass or property damage.

Because the employer failed to provide the site and the contractual construction period expired, the court found that the employer was in breach. The contractor was entitled to terminate the contract.

What constitutes a site handover?

These decisions indicate that, even where a contract does not expressly impose a site-handover obligation, Thai law may focus on whether the failure to provide a usable site affected the contractor’s ability to perform.

A handover is not necessarily complete merely because the employer identifies the site or tells the contractor that it may enter. Depending on the work and the contract, the site may need to be accessible, clearly delineated and free from obstacles that the employer must resolve before the work can begin. The assessment will depend on the nature of the work, the contract terms and the allocation of responsibilities between the parties.

Projects involving multiple work packages or contractors

Site-readiness issues often arise where an employer divides a project among several contracts or work packages. One contractor’s work may need to be completed before the site or relevant part of the work can be handed over to the next contractor. For example, demolition or foundation work may need to be completed before systems installation can begin.

If the earlier work is delayed or defective and requires correction, the subsequent contractor may be unable to start as planned. In that situation, the analysis should not stop at whether the subsequent contractor missed its completion date. It should also consider:

  • when the relevant area was actually available and ready for the contractor;
  • whether completion of the earlier work was a necessary precondition to the contractor’s work; and
  • whether the delay or defects in the earlier work genuinely prevented the contractor from starting or progressing.

The principles reflected in the Thai decisions discussed above may be relevant. If the employer sets the commencement date and is responsible for preparing the site, it may need to make the site available in a condition that allows the contractor to perform the work, taking account of the project’s requirements. Where the employer has structured the project and determined that another contractor’s work must come first, delay or defects in that earlier work may support the argument that the subsequent contractor was not solely responsible for the resulting delay.

That does not automatically establish the employer’s liability. The contractual allocation of risk, the work sequence and the evidence of actual impact must still be examined.

"Providing a site that is ready for the work is part of enabling the contractor to perform its contractual obligations."

Managing the risk of disputes

An unavailable or unready site may not automatically release the contractor from liability. The contractor should be able to show that it was prepared to perform and that a site-related obstacle actually prevented or delayed the work. It should also establish the link between the obstacle and the period of delay claimed.

If some delay was caused by the contractor, the parties or a court may need to distinguish between the causes and periods of delay attributable to each side.

Relevant records may include:

  • written requests for site access or handover, together with proof of receipt;
  • meeting minutes, programmes and documents showing the sequence of work or the relationship between contracts;
  • site-supervision reports, photographs and dated records of site conditions;
  • notices identifying defects or outstanding work by an earlier contractor, and instructions to remedy them;
  • evidence that the affected contractor was ready to proceed, such as records of personnel, equipment and material orders; and
  • notices reserving the contractor’s rights to claim an extension of time, resist or reduce liquidated damages, or seek compensation under the contract and applicable law.

Conclusion

Providing a site that is ready for the work is part of enabling the contractor to perform its contractual obligations. International standard forms such as the FIDIC Red Book address this expressly. Thai law also supports the principle that an employer may be required to prepare and provide the site even where the contract does not state that obligation in explicit terms.

In a project divided among several contractors or work packages, delay or defects in earlier work may affect whether a subsequent contractor could start on time and who bears responsibility for the resulting delay. The outcome will depend on the contract, the circumstances on site and, critically, evidence showing when the site was ready and how the relevant obstacle affected the work.