Senior Associate London
"The case is of key importance to parties that contract under JCT terms for understanding the available grounds for termination following late payment or other specified defaults and will be of interest to employers, contractors and subcontractors across the industry."
The Supreme Court has overturned the decision of the Court of Appeal, finding that the right for a contractor to terminate for a repeated ‘specified default’ will only arise where that right to terminate previously accrued but was not exercised.
In contrast to the Court of Appeal decision, the Supreme Court has significantly curtailed contractors’ ability to terminate under the JCT forms on the grounds of a ‘specified default’.
Factual Background
The facts of the case will be familiar to many readers and further detail can be found in our article on the Court of Appeal decision.
In brief, the dispute arose out of a contract on the JCT Design & Build Contract (2016 edition) form under which Hexagon Developments Ltd (“Hexagon”) employed Providence Construction Ltd (“Providence”) for the construction of a number of buildings in Purley, London.
Hexagon failed to make timely payment under the contract, leading Providence to serve a notice of specified default. Hexagon subsequently remedied the default within 28 days, however, in a subsequent payment cycle, it missed another payment. Providence immediately sought to terminate the contract on that basis, relying upon Hexagon’s repetition of that specified default.
The Contractual Issue
The key question put to the Supreme Court was one of contractual interpretation, namely:
“Can the contractor terminate its employment under clause 8.9.4 of the JCT 2016 Design and Build Form, in a case where a right to give the further notice referred to in clause 8.9.3 has never previously accrued?”
The relevant wording of clauses 8.9.1, 8.9.3 and 8.9.4 read as follows:
Clause 8.9.1: “If the Employer […] .1 does not pay by the final date for payment the amount due to the Contractor in accordance with clause 4.9 and/or any VAT properly chargeable on that amount […] the Contractor may give to the Employer a notice specifying the default or defaults (a ‘specified’ default or defaults).”
Clause 8.9.3: “If a specified default or a specified suspension event continues for [28 days] from the receipt of notice under clause 8.9.1 or 8.9.2, the Contractor may on, or within 21 days from, the expiry of that [28 day] period by a further notice to the Employer terminate the Contractor’s employment under this Contract.”
Clause 8.9.4: “If the Contractor for any reason does not give the further notice referred to in clause 8.9.3, but (whether previously repeated or not):
.1 the Employer repeats a specified default;
or
.2 a specified suspension event is repeated for any period, such that the regular progress of the Works is or is likely to be materially affected thereby,
then, upon or within a reasonable time [28 days] after such repetition, the Contractor may by notice to the Employer terminate the Contractor’s employment under this Contract.”
"Can the contractor terminate its employment under clause 8.9.4 of the JCT 2016 Design and Build Form, in a case where a right to give the further notice referred to in clause 8.9.3 has never previously accrued?"
The court was required to consider whether a right to terminate under clause 8.9.3 needed to have accrued before a right to terminate under clause 8.9.4 would become exercisable.
At first instance, the High Court ruled that a right to terminate under clause 8.9.4 only arose if the right to terminate under clause 8.9.3 had accrued. The judge based his reasoning upon “the natural and ordinary meaning of clauses 8.9.3 and 8.9.4 in the context of the contract as a whole”. He also dismissed submissions that these interpretations would cause unfairness to the contractor, who could theoretically have to endure payment 27 days late in every payment cycle. The judge noted that the contractor “has a battery of weapons available to him to protect his cash flow position”, including statutory interest.
On appeal, the Court of Appeal took the opposite view. Stuart-Smith LJ began by considering clause 8.9.4 “viewed in isolation”. He found that there was no suggestion that a contractor must have had a previous exercisable right to terminate the contract under clause 8.9.3, in order to terminate under clause 8.9.4. The Court of Appeal took the view that the words “for any reason” in clause 8.9.4 were sufficiently broad to cover circumstances where the contractor had not previously issued a further notice to terminate, because the earlier default had been remedied within 28 days and no right to terminate had arisen at that time.
In addition, Stuart-Smith LJ was unpersuaded by the argument that the contractor has a plethora of remedies available to it to offset late payment. In his view, the other remedies failed to be as immediate as full payment on time.
The Supreme Court’s Decision
The Supreme Court judgment began by restating familiar principles of contractual interpretation derived from the leading House of Lords and Supreme Court authority, including:
- the aim of contractual interpretation is to ascertain the meaning which the contract would convey to a reasonable person having all the relevant background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract;
- the words used by the parties are of primary importance so that one must be careful to avoid placing too much weight on business common sense (or purpose) at the expense of the words used; and one must be astute not to rewrite the contract so as to protect one of the parties from having entered into a bad bargain; and
- contractual interpretation involves an iterative process by which each suggested interpretation is checked against the provisions of the contract and its commercial consequences are investigated.
As to the interpretation of JCT standard forms:
- the court found that explanatory notes to a contract may be admissible in evidence as an aid to interpretation, and it was not disputed in this case that the JCT’s Design and Build Contract Guide 2016 was admissible evidence in interpreting the contract;
- industry standard forms, such as the JCT contract forms, are to be distinguished from “take it or leave it” standard forms used by parties with superior bargaining power: there is no such problem of inequality of bargaining power in relation to industry-wide standard forms; and
- in interpreting industry-wide standard forms, the admissible background context may include past decisions of the courts on and practice in relation to clauses in an earlier version of the standard form, although an “archaeology of the forms” is generally to be discouraged.
The Supreme Court found that entitlement to terminate under clause 8.9.4 could not arise without a termination right under clause 8.9.3 having first arisen.
Key to the Supreme Court’s decision was the observation that the opening words of clause 8.9.4 would be superfluous if not for clause 8.9.3. This, the Court said, indicated that the right to terminate under clause 8.9.4 was dependent on the specified default not having been remedied within 28 days prior to the repetition which could trigger termination under clause 8.9.4. In that way, the court decided, the right to terminate under clause 8.9.3 acts as the ‘gateway’ to termination under clause 8.9.4.
It was also the Supreme Court’s view that the consequences of the Court of Appeal’s decision would weigh heavily on the employer. Adopting (incidentally) an opposite example to the hypothetical used before the High Court and the Court of Appeal, the Supreme Court noted that if the employer made only two late payments, only one day late in each case, the contractor could serve a notice immediately following the first late payment and then simply terminate the contract following the second. This was likened to using “a sledgehammer to crack a nut”.
For those reasons, the Supreme Court decided that the right to terminate under clause 8.9.4 can only arise where the prior occurrence of the specified default gave rise to an entitlement to terminate under clause 8.9.3.
Impact of the decision
"An employer can repeatedly fail to make timely payments without giving rise to a contractor’s termination right, provided each failure is remedied within the 28‑day notice period."
Under a standard form construction contract, this interpretation significantly affects the parties’ rights and obligations. It means an employer can repeatedly fail to make timely payments without giving rise to a contractor’s termination right, provided each failure is remedied within the 28‑day notice period required by clause 8.9.3. A contractor’s right to terminate for repeated default will only arise once 29 days or more have passed since the employer has received the notice of specified default.
This reasoning applies equally to all specified defaults listed under clause 3.16 of the JCT 2016. Importantly, this includes breaches of the CDM Regulations. As a result, while CDM Regulation breaches may arise regardless of the contractual framework, the contractor’s ability to terminate will not be triggered if the employer cures each breach within the 28‑day period.
This interpretation somewhat restricts a contractor’s ability to terminate for repeated employer defaults. In practice, contractors may have to continue performing despite recurring breaches regarding both payment and the CDM.
Commentary
The Supreme Court’s decision is a significant one for the industry. Under the relevant JCT contract forms, employers no longer face the prospect of termination by contractors for repeated delays to payment which do not exceed 28 days. However, employers should remain aware that any failure to make late payment may still have serious consequences that fall short of termination of the contract.
To mitigate those risks, employers should consider implementing monitoring systems and/or software to track alignment with payment schedules and establish protocols for swiftly rectifying late payments. Risk management strategies such as these may help to prevent termination rights becoming exercisable by the contractor. Given the importance of the precise wording the contract as noted in Providence, employers may also consider amending the JCT form to clarify the parties’ termination rights and obligations. These amendments may include extended grace periods for late payment beyond the 28 days for which the relevant JCT forms provide.
Conversely, contractors and subcontractors remain exposed to the troubles of repeated late payment. However, as has been noted at several junctures as Providence has proceeded through the courts, remedies and ‘other weaponry’ for late payment other than termination remain available to contractors and subcontractors.
Payees should also be aware of their right to issue a notice of specified default, which remains a clear warning to paying parties not to delay payment. If the opportunity arises, contractors should consider seeking amendments to their JCT contracts including provisions to embolden their termination rights. Seeking legal advice promptly when these situations arise will ensure compliance with contractual terms and can avoid lengthy disputes.
Please do not hesitate to contact us should you have any questions as to how this may impact your project.
Key contacts
Senior Associate London
Partner London
Related insights
Newsletter Commercial Disputes Weekly – Issue 269
Newsletter Commercial Disputes Weekly – Issue 268
Newsletter Commercial Disputes Weekly – Issue 267


