The English Technology and Construction Court has found that the assignment of a sub-contract from a main contractor to an employer upon termination of an EPC contract will, in the absence of express intention to the contrary, transfer both accrued and future contractual benefits.
In doing so, Mrs Justice O’Farrell has emphasised established principles on assignment and novation, and the clear conceptual distinction between them. While this decision affirms existing authority, it also highlights the inherent risks for construction contractors in step-in assignment arrangements.