Partner Madrid
"These decisions mark a significant development for sponsors and investors, offering renewed confidence in Galicia’s regulatory regime and the future of renewable energy deployment in the region."
Watson Farley & Williams (“WFW”), together with CCS Abogados, represented Greenalia Group in its appeals against judgments issued against it by the High Court of Justice of Galicia (“TSJG”) annulling a prior agreement of 18 November 2021 of the Council of the Xunta de Galicia regarding the Campelo wind farm project and related facilities in the Coristanco and Santa Comba municipalities. Said agreement granted both prior administrative authorisation and administrative authorisation for construction, as well as declaring the project of public utility. The Supreme Court (“SC”), however, recently issued Judgments no. 316/2025 and 317/2025 dated 21 March, in which it upheld the aforementioned appeals, annulled the contested judgments as not in accordance with the law, and confirmed the full legality of the aforementioned agreement of the Xunta.
By virtue of Judgments no. 316/2025 and 317/2025, the Supreme Court has established precedent on the following issues:
- When determining whether the installation of wind farms sharing connection facilities should be considered a single project for environmental assessment purposes, the court clarifies and states that “it is common in practice to request and grant authorizations for wind farms located in close proximity to each other and that also share certain elements or infrastructures, as this can be beneficial both from the economic perspective of the developers and the objective of limiting the environmental impact that accompanies, by definition, wind farm installations“. In fact, “the regulations have been promoting the sharing of infrastructures to limit the environmental impact of this type of installation” and “we can affirm that the use of common infrastructures is a technical requirement imposed or favoured by the applicable regulations, and that not always when two or more wind turbine-based electricity productions installations share certain infrastructures or elements, can a breach of the unitary nature inherent to each wind farm be observed“.
- Therefore, the High Court concludes that “The fact that two or more wind farm installations share connection facilities does not necessarily mean that we must consider the existence of a single wind farm project for the purposes of its environmental assessment” and that “The determination of whether, in such a case, the existence of a single wind farm should be considered for the purposes of its proper environmental assessment must be made on a case-by-case basis, taking into account the relevant circumstances, in the light of the applicable regulations and jurisprudence“.
- Applying this doctrine to the case of Campelo, it concluded that “the appealed judgment does not conform to the doctrine we have just mentioned, as it derives the unity of the project for the purposes of its environmental assessment solely and exclusively, from the fact that the three concerned wind farms (Campelo, Bustelo and Monte Toural) share “structures and connections” or “evacuation lines and infrastructures”, without referring to or considering any other concurrent circumstance or the impact of such separation on the adequacy of the environmental assessment produced under the circumstances of the case which, as recorded in the proceedings, was of an ordinary nature, with the corresponding study of cumulative and synergistic effects whose sufficiency or insufficiency is not analysed“.
Key contacts
Partner Madrid
Senior Associate Madrid
Senior Associate Madrid
"The Supreme Court thus made it clear that there can be no fraudulent fragmentation of facilities for environmental purposes by the mere sharing of connection infrastructure."
- The Supreme Court thus made it clear that there can be no fraudulent fragmentation of facilities for environmental purposes by the mere sharing of connection infrastructure.
- On the other hand, although the TSJG judgments annulled the project’s authorisations on the grounds that EU regulations had been violated by allowing the Galician regulations to agree to halve the public information period in the environmental assessment procedure for urgent processing, the Supreme Court reiterates and applies the doctrine established in its Judgment no. 1.768/2023, of 21 December, which already pointed out that “Directive 2011/92/EU, as amended by Directive 2014/52/EU, in its art. 6.6, merely states that “Reasonable periods shall be provided for the different stages, allowing sufficient time to: a) inform […]the public.” At no point does the judgment explain that the reduced period, from thirty to fifteen days, for the public information procedure was or has been insufficient because it has prevented or hindered the public from submitting allegations or that such a reduction could therefore be described as unreasonable“.
- Finally, regarding whether the sectoral reports required for the processing of an environmental impact assessment procedure must be obtained before submitting the project and the environmental impact study to the public information procedure, as argued by the TSJG, the Supreme Court confirms and re-applies the same Judgment no. 1,768/2023, previously cited, which already resolved this issue by clarifying that “The procedure must allow public participation at an early stage, when all options are open, and this participation must be real and effective, but the directive does not impose exactly when the public information must be carried out nor that it must necessarily be done after consultations with the authorities“.
In summary, these judgments have been very positively received as they clarify key industry concerns and confirm the legality of the authorisations for the Campelo wind farm, allowing its construction to resume after being improperly halted for over a year by the High Court of Justice of Galicia. Additionally, they unblock the processing of many other contentious-administrative procedures that are currently suspended due to the prejudicial nature agreed upon by the High Court whilst the Supreme Court resolved the appeals that are the subject of this article.
Key contacts
Partner Madrid
Partner Madrid
Senior Associate Madrid
Senior Associate Madrid